ANALYSIS OF MATERIAL INVENTORY CONTROL THE METROSTATER CONSTRUCTION PROJECT IN DEPOK
Kata Kunci:
EOQ, FPR, Lot For Lot, Wagner and WithinAbstrak
In the last 10 years the construction sector boom has increased rapidly. The Government's Long-Term Plan and the leniency of government policies on investors wishing to invest in Indonesia have stimulated the growth of the construction sector in Indonesia. Increasingly adequate infrastructure encourages entrepreneurs or contractors to invest in public and private projects. One of the private construction projects being handled is the Depok Metrostater Project. This project is located in the city of Depok which has a Transit Oriented Development (TOD) concept. Currently the project is still in the construction stage of the foundation and in its implementation it requires concrete iron as raw material. To ensure material availability, the contractor will perform a scheduled recapitulation of materials according to usage needs. This material scheduling implements material stock inventory control that must be available in the warehouse, so as not to overstock. For this reason, an optimal inventory control analysis is needed through the Economic Order Quantity (EOQ) method, Lot For Lot, Fixed Period Requirement (FPR), and the Wagner and Within algorithms. The comparative results of the inventory method analysis based on the Wagner and Within Algorithm methods provide the most economical results with the minimum total cost of Rp. 583,466,945, - among the other three methods. and Contractors can make efficiency by 35%Referensi
Barry R., dan Heizer Jay. (2001). Prinsip-Prinsip Manajemen Operasi. Jakarta: Penerbit Salemba Empat.
Fahmi, Irham. (2012). Manajemen Produksi dan Operasi. Bandung: Alfabeta
Indiyanto, R. (2008). Perencanaan dan Pengendalian Produksi. Surabaya; Yayasan Humaniora
Matius M.T, Sulistyadi,K, Ratnasari,L, (2020), Perencanaan Sistem Persediaan Bahan Baku Produk X Solar Water Heater Di PT. XYZ, J. Gaung Informatika, Vol 13 (1), pp.12-21.
Miftahus Surur, M., Pudjirahardjo, W.J. & Tanto, H. (2006). Perbandingan Metode Master Production Schedule Ber-lot Size EOQ disertai Hasil Forecasting Terpilih dengan Maximum-Minimum Stock Level (Simulasi Perencanaan dan Pengendalian Persediaan di RS Siti Khodijah). J. Adm. Kebijak. Kesehat, Vol.5 (1), pp.8-15.
Nasution Arman H., dan Prasetyawan Yudha. (2008), Perencanaan dan Pengendalian Produksi, Yogyakarta: Graha Ilmu.
Ristono, Agus .(2009). Manajemen Persediaan. Yogyakarta: Graha Ilmu
Sulistyadi, Kohar dan Iman Basriman, (2018), Sistem Produksi : Industri Manufaktur dan Jasa, Sekolah pascasarjana Usahid Press, Universitas Sahid Jakarta
Diterbitkan
Terbitan
Bagian
Hak publikasi atas semua materi informasi yang tercantum dalam situs jurnal ini dipegang oleh dewan redaksi/editor dengan sepengetahuan penulis. Pengelola Jurnal akan menjunjung tinggi hak moral penulis.
Aspek legal formal terhadap akses setiap informasi dan artikel yang tercantum dalam situs jurnal ini mengacu pada ketentuan lisensi Creative Commons Atribusi-NonCommercial-No Derivative (CC BY-NC-ND), yang berarti bahwa hanya dengan izin penulis, informasi dan artikel Jurnal Jurnal Sustainable Environment Optimizing Industri (SEOI) dapat didistribusikan ke pihak lain dengan tanpa merubah bentuk aslinya untuk tujuan non-komersial.
Setiap terbitan Jurnal Sustainable Environment Optimizing Industri (SEOI), bersifat open access untuk tujuan pendidikan, penelitian, dan perpustakaan. Di luar tujuan tersebut, penerbit atau pengelola jurnal tidak bertanggung jawab atas terjadinya pelanggaran hak cipta yang dilakukan oleh pembaca atau pengakses.